Tuesday, October 25, 2016

THE GHOST COMMUNITY DAY SHSS

By William Yaw Owusu,with reports from Vincent Kubi, Ada; Daniel Y. Dayee, Sunyani; Emmanuel Opoku, Takoradi; Eric Kombat, Tamale & I.F. Joe Awuah Jnr., Kumasi
Saturday, October 22, 2016

The Mahama-led NDC government’s promise to build 200 community day senior high schools (SHSs) before the end of 2016 is beginning to haunt the ruling party as the December 7 general election hits a homestretch.

The major campaign promise is becoming more of propaganda than reality as reports from the regions indicate non-existent of the school projects, eroding the credibility of the government.

President John Mahama on September 5 admitted during the commissioning of one of the newly-built schools at Abodom in the Central Region that he could not complete all the 200 community day schools he promised before his first term ends.

President Mahama who is feverishly campaigning for a second term had promised in 2012 that 200 schools would be built across the country.

Realising that the 200 was too high, he later changed the figures to 123, saying that he could complete all the 123 before the December 7 general election but many of the projects have been stalled. While some have not been started at all, a few had been commissioned by the president.

He said at Abodom in the Agona East District that “In my next term of office (from 2017), by the grace of God, we will complete all the 200 new senior high schools that I promised,” explaining, “As I said, currently, 123 are under construction, and that means that the Central Region will receive additional secondary schools among the remaining over 70 schools that we shall build.”

But, the reports from the regions paint a different picture, indicating that the president might have been misinformed about the reality on the ground.
Most of the schools have not taken off due largely to lack of bud to support the construction.

Ablakwa Contradictions
However, the utterances of Deputy Minister of Education Samuel Okudzeto Ablakwa on the construction of the schools nationwide as promised by President Mahama is giving some sections of the public calls to suspect the government has something to hide.

He has been making contradictory statements in the media since the debate on whether the government is capable of completing the projects on time came up.

Green Book
On page 15 of the NDC’s propaganda-induced Green Book, the ruling party claimed that a $156 million Secondary Education Improvement Programme (SEIP) being sponsored by the World Bank “has been launched and is progressing.”

They stated that under the programme, there will be:
Financing for the construction of 23 community day SHS, improvement in quality and facilities in 175 existing SHS, provision of scholarships to 10,400 needy students 2,300 of whom had already been awarded; and capacity building for 6,500 people as well as mathematics, science and ICT teachers and leadership training for secondary school heads.

Completed Projects
As at June, the Mahama-led government had completed and commissioned less than 20 out of the 200 community day SHSs it promised and the World Bank was sponsoring 23 of them, with the rest being financed by the government of Ghana.

Most of the commissioned schools were the World Bank-funded ones, while the Ghana government ones are struggling for completion because of unavailability of funds – the reason the president cannot fulfill his campaign promise of 200 schools – which has been pegged at 70 by Okudzeto Ablakwa.

Cost of Projects
Interestingly, the NDC government has not yet been able to tell Ghanaians the actual cost of each of the completed schools, not to talk of the entire 200.

In March 2014, when President Mahama amid NDC fanfare, cut the sod for the construction of the first 50 schools; as part of a total of 200 new community day senior high schools to be built across the country, he had insisted all the 50 was going to be completed before the December 7 elections.

Later at another function, Okudzeto Ablakwa confirmed that “there are ten ready, the Ministry of Education has to set the date (for the inauguration). We are building 123 as at now at various stages of completion. Some of them the sites have been handed over, they’ve started the profiling, but the early ones that we started, many of them are in advanced stages of completion.”

“So although we promised 200, we have 123 ongoing, many of them will be ready before elections. We are not waiting to finish all before we populate the schools and so as we are finishing the schools and we are handing over to the Ministry of Education, we are putting the children to school,” he added.

Ablakwa List
On Septemebr 29, after months of confusion on the existence of the number of community senior high schools actually completed, Okudzeto Ablakwa issued a statement claiming that the 123 schools had all been awarded on contract and were at various stages of the project completion.

Strangely, he released the list without indicating which ones had actually been completed and those at the various stages of completion.

Media Interviews
He was captured in a national newspaper recently as saying that 42 of community day SHSs are ready to open for admissions in the current 2016/2017 academic year.

He said 10 had already been inaugurated, while two (Agric Nzema Day SHS in the Ashanti Region and Nemonwora Day SHS in the Agona East District of the Central Region) will be inaugurated very soon and also said that 30 were at various stages of completion and would be done by October. We are in October and the signs are not good as the schools may not be able to admit students because those that have been completed have no teaching and learning materials as well as teaching and non-teaching staff.

Ablakwa was also quoted as saying that nine out of the remaining 30 will be completed before September ends and the remaining 21 will be completed before October ends.

Interestingly, On September 4, this same minister was on Citi FM saying he believes that about 70 of the schools will be ready to admit fresh students in the current academic year and this even contradicted President John Mahama’s 123 schools.

This raises questions that, in effect, only 42 schools may be ready by the end of the year to admit students, even that there are doubts.

Western Region
President Mahama has been able to commission only one out of the 13 schools that the government promised the people of Western Region so far. The commissioning was done at Bamiankor in the Nzema East Municipality (No. 46 on Okudzeto Ablakwa’s list).

At Whindo near Asakae in the Kwesimintsim Constituency at Sekondi Takoradi in the Western Region (No. 100 on the list), the land is lying fallow as there is no activity over there, not even a signpost announcing the project yet Okudzeto Ablakwa listed it as one of the schools which is at ‘various stages of completion.”

When DAILY GUIDE visited the community, it was revealed that there was no such project going on in the area. 

A former assembly member for the area indicated that the project was actually taking place at Whindo, about 15 minutes’ drive from Asakae. 

When DAILY GUIDE got to Whindo, it was raining heavily but the residents were eager to speak with the paper.
Some of the residents claimed that it was not true that the project was at any stage of completion. 

“In fact, we have heard that such a project is coming to Whindo but the truth is that the assembly has now acquired the land and had not even finished paying compensation to those whose farm produce are on it. No project has started on it,” the residents told DAILY GUIDE

Brong-Ahafo
Not more than three of the 16 schools promised the people of Brong-Ahafo Region have been commissioned. At Danyame in the Dormaa Central Municipality, the contractor had abandoned the project and left the half building to the mercy of the weather.

The project at Krobo in Techiman Municipality is almost completed as the building is receiving its final facelift when DAILY GUIDE visited, but in many other areas where the projects have been sited, there is either little work or no action at all.

Ashanti Region
Out of the 13 schools promised the Ashanti Region, four are said to have been completed, while eight are uncompleted and but the one at Manfo in Ahafo Ano North (No 52 on the list) has not started at all, yet Okudzeto Ablakwa is saying it is being done.

Easter Region
In the Eastern Region, the NDC government promised 13, but not more than one has been reportedly been commissioned.

At Abomosu in the Atiwa District (No 67 on the list), the site has been demarcated behind the Presby School JSS but there is no action over there. The Abomosu story is similar to that of many other projects in the region which are in limbo.

The contractor is said to be chasing money to undertake the job.

Central Region
In the Central Region, not more than three of the 13 schools promised have been commissioned.

Those officially commissioned by President Mahama include Abodom in Agona West (No. 20) and Ekumfi Otuam (No. 21) respectively.

Diaso in the Upper Denkyira West District (No. 19) is almost completed. However, at Kobina Ansa in Mfantsiman (No. 61) for instance, the designated land is covered by weed and there don’t seem to be any activity.

Volta Region
In the Volta Region, the NDC government promised the people 12 schools but not more than three have been officially commissioned.

At Avenorpeme in Akatsi South (No. 41), the project is almost completed, the one at Nkwata South (No. 43) has been commissioned but some parts of the building, according to media reports, are defective.

The Agblekpui project in Ketu South (No. 94) is halfway done, while the Damanko project in Nkwanta North (No. 42) is progressing, but also not completed.
At Kwamekrom-Abornukope in the Biakoye District, the school was inaugurated by the president, while in Abuadi & Tsrefe in the Adaklu, there is an appreciable progress, but in Ziope in the Avetime District, the buildings are now being raised.

Greater Accra
In the Greater Accra Region where the Mahama-led NDC government promised to build 10 schools, not a single one has been commissioned.

For instance, at Teshie in the Ledzokuku Krowor Municipal Assembly (LEKMA), Accra (No. 71), a giant billboard has been erected with the photographs of President Mahama and the MP for the area, Benita Okiti Dua, but there is nothing on site.

At Ada East District, the site for the school project has been located between Ashigbekope, Kpodokope and Kasseh (No. 73), but there is absolutely no ongoing construction at its site at Koluedor. 

The school is nowhere to be found, as there is no site for the project in the area because the leadership of the area are at loggerheads with each other over the location of the school.

Information gathered by DAILY GUIDE indicated that the former DCE wanted the school to be built in his village in Koluedor, as the MP for Sege, Christian Corleytey Otuteye, wanted it done at Agblabanya with the community, including the chiefs have also made their request for the school to be built in between Goe and Agblabanya.

The above misunderstanding had led the area to be without a site for the project to construct the school.

At Ashaiman where the school is located at Community 22, the project is at roofing level, but the administration block is yet to commence and plastering on the building has also not started.


In Tema Metropolis at Lashibi (No. 72), there is positive progress even though there is still more work to be done on the building, but at the Kpone Katamanso (No. 110), the building is at the foundation stage.

Northern Region
The president promised 14 schools for Northern Region and the government is yet to commence construction in majority of the lands reserved for the projects.

At Nasia (No. 78), the land remains fallow even though the people were told the school was going to be built within eight months.

 A visit by DAILY GUIDE to the area revealed that the project has been abandoned and left unattended to, and it has been covered by weeds.

The assemblyman for the area, Alhassan Salifu, told DAILY GUIDE that Nasia and its surrounding communities have had their hopes dashed by the failure of the members of parliament (MPs) and the contractor’s inability to start the building of the community day senior high school.

In a phone interview with DAILY GUIDE, the contractor of the project, Stephen Okutah, said, “Honestly, we started something on the site, we laid the pipes and cleared the land but later the funds were not flowing. We were later told to continue with the project if we have money and we don’t have money.”
  
Upper East
Few of the 11 schools for Upper East promised by the Mahama-led government are all at different stages of completion, but construction is yet to take place in majority of the sites.

Construction has started on the site for Gambigo Community SHS (No. 85) located at Zuarungu in Bolgatanga East Municipality and a similar situation at Bongo Azeem-Namoo (No. 87) in the Bongo District, but they are all yet to be completed.

Upper West
The president promised eight schools for Upper West, but there is no indication that any of them has been commissioned.

Majority of the projects have either been abandoned or at early stages of construction, with some no action at all due to non-release of cash.

No comments: